Company business overview

Assets

Installed capacity

21 427MVA
Length of transmission lines
59 337km.
Substations 35-110 kv
373pcs 13 742MVA
Transformer substations 6-35 kv
14 770pcs 7 686MVA

Company business overview

Operational results

Productive power supply

28 975 mln kWh
Connected capacity
320,6 mW

Company business overview

Financial results

Revenue

37 009 RUB mln
EBITDA
8 630 RUB mln
Net profit
1 417 RUB mln

Company business overview

Investments

Capital Investments

15 061RUB mln
Commissioning of capacities
996MVA
1713km

ADDRESS OF THE CHAIRMAN OF THE BOARD OF DIRECTORS TO SHAREHOLDERS

Nikolay N. Shvets

JSC Lenenergo launched the first stage of the most important program for renovation of the cable network of St. Petersburg in 2011.

Read more

ADDRESS OF THE DIRECTOR GENERAL TO SHAREHOLDERS

Andrey V. Sorochinskiy

The first year of modernization of technological connections testifi ed to the Company's making the correct direction -- we have significantly reduced terms of all key processes of technological connection, and gotten rid of lines to file an application -- now it's a question of a day, rather than several months.